Self-Build Dwelling
Gatehead

Murdoch Construction were commissioned to undertake the build of this 4 bedroom dwelling house in Gatehead, Ayrshire following a recommendation by a previous client.

The contract price was negotiated and build programme was set at 20 weeks. Throughout the contract period various addition and change requests were made by the client, these were costed and agreed and without affecting the build programme.

The project was completed 2 weeks prior to target, on budget and to the complete satisfaction of the client.